The latest update on the City of Bainbridge’s Lake Douglas East sewer project:
Paving is complete on Thomas Drive and along Twin Lakes.
Crews are continuing to run the 10” main towards College Road.
Crews are currently working in Back Lake Circle and Ashton Way (laying pipe)
Crews have worked to smooth the cuts in College Road.
Residents along Lakewood Drive and Lakewood Court will lose water service tomorrow, October 2 from 8:30 a.m. – 11:30 a.m.