A sign thanks City of Bainbridge Public Services employees in front of a home on Thomas Drive, which was re-paved last week as part of the City of Bainbridge's Lake Douglas East sewer project.
 

Archived Story

City making progress on Lake Douglas East paving

Published 3:04pm Saturday, September 29, 2012

The latest update on the City of Bainbridge’s Lake Douglas East sewer project:Brannon

Paving is complete on Thomas Drive and along Twin Lakes.

Crews are continuing to run the 10” main towards College Road.

Crews are currently working in Back Lake Circle and Ashton Way (laying pipe)

Crews have worked to smooth the cuts in College Road.

Residents along Lakewood Drive and Lakewood Court will lose water service tomorrow, October 2 from 8:30 a.m. – 11:30 a.m.

For updates, people can follow our facebook page (www.facebook.com/BainbridgeGA), twitter (www.twitter.com/bainbridgecity) or our blog (www.bainbridgecity.com).  Citizens can also receive updates straight to their inbox by emailing cvb@bainbridgecity.com and asking to be added to the sewer project email list.